PROJECT AUTHORIZATION | PACKET ID: N/A |
CONTRACT ID | EMARS PROGRAM CODE | AUTHORIZATION NO: | |
48291 | 14 | ||
It is hereby ordered that the project herein described be undertaken and accomplished within the funding level authorized. |
PROJECT ID | PROJECT ID NUMBER | FEDERAL PROJECT NUMBER | 6 YR PLAN ITEM NUMBER | 6 YR PLAN ITEM PARENT NUMBER |
097 0015 014-017 |
NHPP 0151 074 |
10-00269 | 10-00269.01- |
PROJECT TYPE | PROJECT LENGTH | NUMBER OF BRIDGES | SYSTEMS |
MAJOR WIDENING | 2.361 MI |
PROJECT PHASE & RESPONSIBILITY |
PLANNING | DESIGN | RIGHT OF WAY | UTILITIES |
DOH | DOH | DOH | ||
CONSTRUCTION | TITLE DEEDED TO: | MAINTENANCE | OTHER | |
DOH/CONTRACT | DOH | DOH |
FUNDING & TIME ACCOUNTABILITY |
PARTICIPATING AGENCIES | |||||||
FEDERAL | STATE | DOH | LOCAL | OTHER |
ITEM NUMBER | PHASE | FUND | PROGRAM | FEDERAL FISCAL YEAR | STATE FISCAL YEAR |
||
FEDERAL APPR CODE |
CURRENT FUNDING REQUEST | ||||||
10-269.1 | C | 1200 | FD52 | 2018 | 2018 | Z001 | $7,264,000.00 |
CURRENT FUNDING REQUEST TOTAL: $7,264,000.00 |
AUTHORIZATION SUMMARY FOR THIS 10-1 SERIES |
PHASE | TOTAL AUTHORIZATION TO DATE (INCL. CURRENT REQUEST) |
PLANNING | $0.00 |
DESIGN | $3,289,000.00 |
UTILITIES | $2,775,000.00 |
R/W | $7,000,487.00 |
CONSTRUCTION | $54,185,564.00 |
NON-HIGHWAYS | $0.00 |
Total: $67,250,051.00 |
REMARKS: | THIS MOD. PROVIDES ADDITIONAL CONSTRUCTION FUNDS TO COVER CHANGE ORDER #4 ($6,863,703.84), ROADWAY EXCAVATION AND OTHER ITEMS TO EXTEND THE EXCAVATION LIMITS APPROXIMATELY 1000 FEET TO ALLOW FOR COMPLETE EXCAVATION (RATHER THAN PARTIAL) OF A SIDE HILL CUT. |
Project Approval Recommended By: PCL 5/17/2018 |
Signed and Approved by: RG 5/20/2018 |
AUTHORIZATION LOCATION | ||||||
ITEM NO. | COUNTY | DIST | FACILITY NAME |
ROUTE | LENGTH | SCOPE |
10-00269.10 | PERRY
|
10 | KY 15 | KY 15 | 2.361 MI | IMPROVE SAFETY, UPGRADE GEOMETRICS, AND ADDRESS CAPACITY ISSUES FOR KY 15 FROM MORTON BOULEVARD TO BONNYMAN. |